Project JupiterTop story
Project Jupiter's developer and the state ask to cancel the Dec. 7 air permit hearing
The permit fight moved from deadline dispute to delay request
- Oct. 22State attorneys call the revised application "not ready for primetime."
- Oct. 23Developer says it has not waived the Nov. 23 deadline.
- Nov. 3Developer and state ask to vacate the hearing and its deadlines.
- Nov. 23Decision deadline on air permit No. 10883, which the developer has waived.
- Dec. 7Public hearing was set to begin at the Sunland Park Multi-Generational Center.
Sources: Organ Mountain News, KRWG Public Media
If you've been following Project Jupiter, the Dec. 7 hearing on its air quality permit may not happen that day. Yucca Growth Infrastructure and the Environment Department's Air Quality Bureau filed a joint motion Nov. 3 asking the hearing officer to vacate it. As of Thursday morning, Organ Mountain News could not verify an order granting the request.
The developer also waived the Nov. 23 decision deadline, a reversal from its Oct. 23 filing. The state says it needs more time to review the developer's October revisions. The Santa Fe New Mexican reports the permit looks likely to slip into the new year, when Gov.-elect Deb Haaland takes office.
- Permit: No. 10883, still under review
- Waiver: not an approval of the permit
- New hearing date: depends on the state's technical review
- Dec. 7 hearing: not confirmed canceled as of Thursday morning
Oracle said in October that its revised Bloom Energy fuel cell plant design would cut emissions by about 35%. Environmental advocates have called the changing plans a "moving target" that deserves more scrutiny.
35%emissions cut Oracle says the revised fuel cell design would bring
Oracle announced the revisions to the Bloom Energy fuel cell plant in October.
Source: KRWG Public Media