The Blue Line extension opens Monday, six weeks early

The Daily Las Cruces teamFrom today’s edition · 1 min read · 2 sources

ShareEmailFacebookX

The transit authority will open the Blue Line extension on Monday, six weeks ahead of schedule and $41 million under its budget. The signed off on the final safety review on Thursday night.

What changes for riders

  • Four new stations between Ridge Avenue and the riverfront
  • Trains every six minutes at rush hour, down from every ten
  • Free rides on the extension through Oct. 4

“We said spring of next year. The crews said September, and the crews were right.”

Dana Whitfield, general manager

Sources: The Morning Ledger, Transit Authority